Barton Peveril College, Rose Cafe, Eastleigh

Client

Barton Peveril College

Form of Contract

JCT Design and Build

Duration

12 Weeks

Architect

Stride Treglown

M&E Consultant

Ramboll

Strip-out and and re-fit of the former Fitness Suite within the ground floor of the Rose Building, to create the Rose Cafe including the installation of a commercial kitchen. 

The works were required to take place during periods when the college was fully occupied with both students and staff. 

Ascia were in daily communication with the college to make sure that they continued to operate with the minimum disruption to their operations.

Education

Contact

Ascia Construction

The Portico, Stansted House, Stansted Park, Rowlands Castle, Hampshire PO9 6DX

 02392 006 344

Safe-Contractor-Approved-Certification       

 linkedIn-logotwitter-logo

Latest News

Hastoe Housing commencement event

Hastoe Housing commencement event

Ascia were delighted to attend the commencement event for the 8 new affordable homes for Hastoe Group on the site at Botley Road, Curdridge. We look forward to working with Welling Partnership LLP, mh Architects and Paul Basham Associates.

Ascia to cycle from London to Amsterdam for Prostate Cancer UK

Ascia to cycle from London to Amsterdam for Prostate Cancer UK

In aid of Prostate Cancer UK, members of the Ascia Team are taking part in a sponsored cycle ride from London to Amsterdam. The money raised will fund lifesaving research to help beat prostate cancer, a disease affecting one in eight men in the UK. Below is a link to...