Duration
52 Weeks
Architect
Boyle & Summers
Engineer
Scott White & Hookins
M&E Consultant
Subcontract
Demolition of an existing dilapidated storage building, and construction of a new 50,000 Sq Ft fully automated racked storage building just under 18m high.
This was a two-stage tender, delivered on time and in budget.
The site footprint is the building area, so Ascia utilised a neighbouring building for their office and welfare facilities during the build.
The work was carried out adjacent the existing live factory which works 24/7.
The Building has been built to BREEAM Very Good Standards .
Commercial & Industrial