Royal Close

Royal Close Chichester Client Chichester Greyfriars Housing Association Form of Contract JCT Design & Build Duration 40 Weeks Architect Cover Storey Architects M&E Consultant Subcontract Design Design and construction of 8 new flats with enhancements to the site...

UoC Health Sciences

University of Chichester Health Sciences Client University of Chichester  Form of Contract JCT Design & Build Duration 14 Weeks Architect Stride Treglown M&E Consultant Subcontract Design Refurbishment of the existing ‘ArtOne’ building to provide Health Science...

Fareham College T Levels

Fareham College T Levels 2021 Client Fareham College Form of Contract JCT Design & Build Duration 8 Weeks Architect Cover Storey Architects M&E Consultant Subcontract Design Design and build of refurbishment works to D Building to deliver the Health and Sciences T...

St. Andrews CE High School

STEM Refurbishment Client St. Andrews CE High School Form of Contract JCT Design & Build Duration 13 Weeks Architect Kendall Kingscott Engineer Kendall Kingscott M&E Consultant Subcontract Design Refurbishment of science labs and STEM classroom including new...

Donnington Business Park

Donnington Business Park Client MTS Pension Fund Form of Contract JCT Design & Build Duration 34 Weeks Architect HNW Architects Engineer Archibald Shaw M&E Consultant ION Consulting Design and construction of five new retail units on a industrial park in...

BPC Rose Theatre

Barton Peveril College Rose Theatre Client Barton Peveril College Form of Contract JCT Design & Build Duration 14 Weeks Architect Stride Treglown Engineer Scott White & Hookins M&E Consultant Milieu This £1m project was completed in 14 weeks, with the full...